Preparing Your Site for a Generator Delivery: Checklist
Short answer
Before a generator delivery, confirm the lorry can reach a firm, level parking spot close to the drop point, clear the landing area, check for overhead cables, have the plinth or base ready and level, and book your electrician for connection. Send the set's weight, dimensions and photos of the site in advance. A prepared site keeps the delivery to the planned time and the quoted price.
Why preparation matters
Most generator delivery problems are not about the generator. They are about the site: a car parked in the only space the lorry can use, a plinth that is not cured, a gate narrower than expected or a cable crossing the lift path. Each one either delays the lift or stops it altogether, and a lorry and crane standing idle are expensive.
Good preparation also makes the lift safer. Crane operators need firm ground under their outriggers, a clear swing path and a landing area free of people. The checklist below covers what we ask every customer to sort before the delivery day.
Access for the vehicle
Check the route from the public road to the parking point. A rigid HIAB lorry is long and heavy, typically needing a road or yard that takes a large goods vehicle, at least the width of a normal gateway and clear headroom under barriers, canopies and trees. Articulated vehicles carrying containerised sets need even more space.
The parking point should be as close as possible to the drop point, on hard standing such as concrete or tarmac. Tell us about speed humps, height barriers, weight limits on internal roads and anything that changes on the day, such as market stalls or school traffic.
- Measure gate widths and headroom on the approach
- Keep the lorry's parking area clear of cars and skips
- Confirm the ground is hard and level for outriggers
- Mark manholes, drains and cellars near the parking area
- Tell us about height barriers and weight-restricted roads
The landing area and base
The generator needs a level, strong base. For permanent standby sets that is usually a concrete plinth designed for the weight, often with a bund or the set's own bunded base tank containing any fuel leaks. Concrete must be cured before it takes the load, so do not pour the plinth the day before.
Make sure the set will fit with room around it for maintenance access, airflow and the exhaust. The manufacturer's installation guide gives clearances. For temporary hire sets, level ground with good drainage, away from building openings so exhaust fumes cannot enter, is the minimum.
| Check | What good looks like | Why it matters |
|---|---|---|
| Plinth or base | Level, cured and sized for the set | Stops rocking and settlement |
| Clearance | Space for doors, airflow and exhaust | Servicing and safe running |
| Exhaust direction | Away from windows, vents and doors | Keeps fumes out of buildings |
| Cable route | Agreed with the electrician | Avoids moving the set later |
| Fuel access | Tanker can reach the fill point | Refuelling without disruption |
Overhead hazards and the lift path
Walk the lift path from the lorry to the landing point and look up. Overhead power and telephone lines, tree canopies, building overhangs and scaffolding all affect how the crane can work. Power lines are the most serious hazard, and lifts near them need specific planning.
The area under the load must be kept clear of people during the lift. On busy sites, that means barriers and a banksman, and on public pavements it may mean a council licence and pedestrian management. Tell us early so the right arrangements are in place.
Electrical connection and fuel
The haulage crew places the generator; connecting it is electrical work for a competent electrician. For permanent installations connected to a building's supply, the installation should comply with BS 7671 and include changeover arrangements that stop the set back-feeding into the public network. Book your electrician to attend on or soon after the delivery day.
Ask whether the set will arrive with fuel. Many travel with a small amount in the base tank, and a tanker delivery can be arranged once it is in position.
On the day
Have someone on site who knows where the set is going and can make decisions. They should meet the driver, confirm the position and sign the delivery note. Take photographs of the set before and after the lift, and check it for damage before the lorry leaves. If an old set is being removed, make sure it has been disconnected and isolated by your electrician beforehand, so the crew can lift it out straight away.
Make sure site rules are shared before the day. If the crew needs an induction, a permit to work, high-visibility clothing beyond the normal kit or a specific arrival window, tell us when booking. Hospitals, schools, airports and data centres often have security checks at the gate that add time, and a driver arriving without the right paperwork may be turned away.
Information to send when booking
The more we know in advance, the more accurate the price and the smoother the day. Send the generator's make, model and kVA rating, its weight and dimensions from the spec sheet, and photographs of the parking area, the route and the landing point. Mark the landing point on a site plan if you have one.
Include contact details for the person on site, preferred dates and times, and any restrictions on access. If you are unsure about something, such as ground strength or whether a cable is live, say so. We would rather plan around a question than find out on the day.
Questions people also ask
How much space does a HIAB lorry need to deliver a generator?
It needs room to park on firm, level ground close to the drop point, with space for its outriggers to extend fully on both sides. That is typically a few metres beyond the lorry's own width. Send photos and measurements of the parking area and we will confirm whether it works.
Can a generator be placed on grass?
A temporary set can stand on firm, level grass for short hire periods, ideally on boards or a ground mat with a drip tray. Permanent standby generators need a concrete plinth or prepared base designed for the weight. The lorry itself should not park on soft ground without trackway.
Who connects the generator after delivery?
A competent electrician connects the generator. The transport crew delivers and positions the set but does not carry out electrical work. For building connections, the installation should follow BS 7671, including measures that prevent the generator feeding power back into the public network.
Written and checked by the Generator Transport team. Read our editorial policy.
More guides
How Much Does Generator Transport Cost in the UK?
Generator transport in the UK costs £120–£280 locally for a portable set up to 60kVA, £350–£700 for a 60–200kVA canopied set moved by HIAB and…
HIAB or Mobile Crane for a Generator Lift? A Plain Guide
A HIAB lorry is usually enough for portable and canopied generators up to around 200–500kVA when the drop point is close to where the lorry can park.…
Standby Generator Installation Moves: What Happens
A standby generator installation move starts with a site survey and a lift and rigging plan. The old set is disconnected by an electrician, drained…
Transporting Generators: Fuel, Load Securing and Safety Rules
When generators are moved by road, diesel in the base tank is a dangerous good under ADR, so fuel levels and tank security must be managed. Sets must…